C&E Gravel & Concrete plans to build an asphalt plant on hwy 53
Here are the facts!
C&E Concrete PO Box 2547 Milan, NM 87021Permit NO. 3324 Site: Highway 53, Mile marker 52, Sec 33, T10N, R13WTEMPO Agency Interest ID NO. 24829
Cibola County Manager Office - David Ulibarri 1-505-285-2510
§ Plant at Hwy.53 location.
§ Permit No. 3324
§ TEMPO Agency Interest ID No. 24829
Operation schedule: 6 am to midnight, 365 days per year
Estimated emission rates:
Fugitive road dust and material handling
TSP 24.19 lbs per hour, 36.8 tons per year
PM-10 11.89 lbs per hour, 19.8 tons per year
Nitrogen Oxide (NOX) 28.94 lbs per hour, 73,2 tons per year
Sulfur Dioxide (SO2) 64.98 lbs per hour, 95.0 tons per year
Carbon Monoxide (CO) 27.15 lbs per hour, 48.5 tons per year
Volatile Organic Compounds 8.86 lbs per hour, 15.7 tons per year
TOTAL EMISSIONS: 166.01 pounds per hour – 1.5 TONS PER DAY
547.5 tons per year
There is no information provided regarding water usage for this proposed operation.